Pugwash Water System Update

In our last update we advised that during the commissioning process operators had become concerned with the reliability of the chlorine injection system and that chlorine skid equipment was ordered. We have now been advised that the equipment is anticipated to be delivered April 23rd. Contractors are on standby to begin installation on that date.

 

We had previously advised that air release valves were being replaced and those installations have been completed. It is anticipated that this will aid in the mitigation of the aesthetic issue of aeration.

Staff continue to familiarize themselves with the system in anticipation of distributing water.

The next planned update regarding the status of the Pugwash Water System is following the meeting with the contractors and project management group that will take place on Tuesday, April 16th, 2019.